AZTEC was retained by GCL Solar Energy as the Owner’s Engineer to provide independent engineering services for the Guayama Solar Plant. The scope of services was broken into several stages. Stage 1 was the initial due diligence of the project. AZTEC performed a review of the technical documents, permitting documents, Power Purchase Agreement with the Puerto Rico Electric Power Authority (PREPA), additional legal documents and property contracts. Stage 2 was the review of all final design documents needed to obtain the construction permits. Stages 3 and 4 of the project will be the Provisional Commissioning Review and the Final Commissioning Review after the plant energization.